Review item / Content and consequence
Review item Content and consequence
Adopted basis for the exercise Assumed NPR 7150.2D / Class C / SWE-071 invoked. Review scope: consistency of this changed requirement and its linked plan.
Previous promise, VIEW-UPDATE r1 Update the displayed reading when a new valid reading arrives while connected.
Added promise, VIEW-UPDATE r2 Keep ordinary updates and resume them automatically after interruption and restoration, without a manual application restart.
Current linked content, VIEW-PLAN r1 Keep the connection available, supply a new valid reading and observe the display update. No interruption or restoration is planned.
Recovery evidence available The illustrative texts expose missing planned recovery coverage. No normal-operation or recovery result is supplied.
Next decision Settle the recovery observation criterion and assign the plan update. Recommend deferring reliance on this material as a demonstration of recovery; actual disposition is UNRECORDED.

The texts and revision labels are chosen teaching material. Plan changes are proposed, verification is NOT EXECUTED, and no software failure or repair is observed. Read the complete record.

01 / Establish the applicable basis

What does NPR 7150.2D require you to establish first?

NPR 7150.2D, NASA Software Engineering Requirements, covers software acquisition, development, operation, maintenance, retirement and management, including supporting lifecycle work. It does not prescribe a single lifecycle model. This guide examines one small part of that work: whether verification still addresses a changed requirement. Preface, P.1–P.2; section 1.1.4.

Establish applicability and authority

The directive applies internally to NASA Headquarters and Centers, including their specified facilities. External obligations depend on incorporation. For existing projects, P.2.c–e includes determinations about current and future phases and a nonretroactivity provision. A current edition does not, by itself, require recreating every historical artifact. More stringent governing requirements remain relevant. Preface, P.2.

Use the actual classification determination for the system or subsystem. SWE-020 calls for the highest applicable classification under Appendix D; a short class description is insufficient to assign one. Retain the classification, RMM and independent assessment records required by SWE-176. Sections 3.5.1–3.5.2; Appendix D.

In Appendix C, X means invoked for that class; a blank means optional or not invoked by this NPR. A blank does not prohibit the activity or remove another governing obligation. Tailoring an X requires the designated authority and the applicable rationale, risk evaluation, concurrence and approval records. Check the authority column and the full approval process. Chapter 2's role obligations sit outside Appendix C and retain their own conditions. Sections 2.1.8 and 2.2; section 1.3.1.

Keep the records separate

Different records answer different questions about the same change. These distinctions do not require separate files.

Record / Question it answers
Record Question it answers
NPR Requirements Mapping Matrix Which NPR provisions apply, how will they be addressed, and what tailoring has the designated authority approved?
Software artifact trace Which project requirement relates to which verification, design or other applicable artifact, and at which revision?
Verification plan or procedure What will be examined, by which method, against what criterion?
Performed verification and evaluation What was actually examined or observed, and what conclusion does that evidence support?
Authorized disposition Who decided how the evidence may be relied on, for which scope and conditions?

SWE-052 addresses bidirectional artifact traceability. SWE-053 addresses requirement changes; SWE-054 addresses inconsistencies and their closure; SWE-071 addresses consistency of test and verification plans and procedures. Each provision has its own applicability. Section 3.12.1; sections 4.1.5–4.1.6 and 4.5.7.

Table 1 orientation for already classified software. Read the actual requirement and mapping before applying this summary.

Software class / Relationships marked in SWE-052 Table 1
Software class Relationships marked in SWE-052 Table 1
A, B and C Higher-level/software requirements; requirements/system hazards; requirements/design components; design components/code; requirements/verification; requirements/nonconformances.
D Requirements/system hazards, requirements/verification and requirements/nonconformances.
F Higher-level/software requirements, requirements/verification and requirements/nonconformances.
E No Table 1 column; the Appendix C SWE-052 cell is blank.

This is an orientation to Table 1 and the SWE-052 mapping row, not a complete applicability assessment. Do not invent hazards or nonconformances to fill a relationship. Verification can include suitable review or analysis; the current D wording is broader than the older “test procedures.”

This review has a smaller scope than a generic RTM tutorial or a whole verification plan/report. An SRR examines whether a requirement-set revision is an adequate basis for the next stage. NASA-STD-8739.8 covers complementary software assurance and safety responsibilities. NPR section 3.6.1.

02 / Use the free human record

Free change-to-verification worksheet

Copy this complete record into a document or issue. Start by filling sections 2–3 with the old/new wording and relevant linked content; complete section 1 before deciding reliance. Use UNKNOWN, UNASSIGNED or UNRECORDED where material is missing; use NOT APPLICABLE, with a reason only when justified.

This is a human worksheet for one decision. It is not an official complete RMM or an AI prompt. Chapter 6 does not mandate this format or a fixed number of fields. Section 6.1.

CHANGE-TO-VERIFICATION REVIEW

1. Decision, adopted basis and authority
Software/system scope; claim and pending decision:
Adopted NPR edition and adoption/incorporation record:
Current official edition check and source:
Classification determination, scope and supporting record:
Applicable SWE provision(s), RMM row/revision and implementation approach:
Relevant tailoring or applicability decision and approval record:
Authority for that mapping/tailoring; authority for the pending decision:
Missing basis/authority records and who will obtain them:

2. Requirement change
Project requirement identifier and owner:
Old revision, exact relevant wording and location:
New revision, exact relevant wording and location:
Change authorization/status and record:
Added or changed condition and required outcome:
Unresolved meaning, observation window or acceptance criterion:

3. Linked content, planned criterion and available evidence
Linked plan/procedure/analysis identifier, revision and location:
Relationship meaning; how it can be followed in both directions:
Actual relevant steps, assertions or analysis content inspected:
Planned observation and criterion for the changed behavior:
Available performed evidence, scope, relevant revisions and location:
Recorded evaluation, if any; missing or unresolved evidence:
Does the content/evidence address the change? Explain the supported scope:
Historical evidence retained, if any, and limits on its reuse:

4. Closure and responsibility
Required clarification or content change, if any:
Required relationship/revision maintenance, if any:
Later verification, evidence retention and evaluation needed, if any:
Action owner(s), reviewer and closure criterion:
If unassigned: appointing role, appointment action and its status:
Action status: PROPOSED / IN PROGRESS / COMPLETED, with supporting record:

5. Recommendation and actual disposition
Evidence judgment: supported / partly supported / insufficient /
contradicted / unresolved applicability; give reasons and scope:
Recommended reliance and next decision:
Actual disposition: decision, designated authority, record and conditions;
write UNRECORDED if no decision record exists:
Remaining limitations and what would reopen this review:

Record support when current evidence addresses the change; a new test is not automatically necessary.

03 / Inspect the gap and correction status

Worked example: the recovery promise outgrew the plan

A verification lead needs to decide whether the viewer's linked verification supports its revised recovery promise. To address that promise, verification must examine updating after interruption and restoration. The linked plan instead exercises only an available connection. The documentary comparison finds missing planned coverage of the new condition. It supplies no observation of whether the software actually recovers.

The following record contains the complete relevant teaching texts. It assumes an adopted D/Class C basis invoking SWE-071 and examines the requirements-to-verification relationship described by SWE-052. No real project's classification, contract, approval or appointment is established by those assumptions.

Filled documentary review

CHANGE-TO-VERIFICATION REVIEW: ILLUSTRATIVE READING VIEWER

1. Decision, adopted basis and authority
Scope: one reading viewer behavior, VIEW-UPDATE r2, and its linked
verification plan, VIEW-PLAN r1. Pending decision: may this material
support reliance on the added automatic-recovery promise?

Teaching basis: assume NPR 7150.2D is adopted, Class C is the applicable
mapping, and SWE-071 is invoked without relief. The reviewed trace is the
SWE-052 software-requirement-to-verification relationship, also assumed
applicable without relief. Other relationships and provisions are outside
this review's assessment.

Current official basis: NODIS identifies D as CURRENT at the 31 October
2026 source check, effective 8 March 2022, expiration 8 March 2027.
Source: NODIS NPR 7150.2D directive history:
https://nodis3.gsfc.nasa.gov/directive_history.cfm?Internal_ID=N_PR_7150_002D_&page_name=main

Teaching RMM implementation approach for SWE-071: maintain verification
plan/procedure content consistent with the software requirements.
Provision: NPR 7150.2D section 4.5.7:
https://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7150_002D_&page_name=Chapter4
Actual adoption/incorporation, classification, RMM revision, tailoring
and approval records: NOT SUPPLIED. The assumptions above are not approvals.
Actual mapping/tailoring authority and decision authority: UNKNOWN.
Proposed basis action: project manager or delegated responsible role obtains
the governing records and identifies the designated authorities.
Status of that action: NOT PERFORMED.

2. Requirement change
Project behavior requirement: VIEW-UPDATE. Actual owner: UNASSIGNED.
The following r1 and r2 texts are chosen teaching statements; their
location is this filled record, not an external project repository.

Old text, VIEW-UPDATE r1:
"While the reading connection is available, the viewer shall update the
displayed reading when a new valid reading arrives."

New text, VIEW-UPDATE r2:
"While the reading connection is available, the viewer shall update the
displayed reading when a new valid reading arrives. After the connection
is interrupted and then restored, the viewer shall resume these updates
automatically, without a manual application restart."

Change status: r2 is the selected review target for this exercise.
Actual change authorization: UNRECORDED.
Added condition: interruption followed by restoration of the connection.
Required outcome: automatic resumption of reading updates without a manual
application restart.
Unresolved criterion: the observation window and timing acceptance rule
for that resumption. No accepted numeric bound is supplied.

3. Linked content, planned criterion and available evidence
Teaching forward link: VIEW-UPDATE r2 -> VIEW-PLAN r1.
Meaning: this plan is recorded as intended verification of VIEW-UPDATE.
Reverse navigation: VIEW-PLAN r1 is the recorded verification target for
VIEW-UPDATE r2. This relationship locates the reviewed artifacts; its
existence does not establish that the plan covers r2.
The complete relevant plan content is reproduced here:

VIEW-PLAN r1, normal-operation check:
1. Keep the reading connection available.
2. Supply a new valid reading distinguishable from the displayed reading.
3. Observe that the display updates to the new reading.

Content finding: no step interrupts or restores the connection. The plan
does not address the added recovery condition, even though a link exists.

Proposed recovery observation: interrupt the connection, restore it,
supply a distinguishable NEW valid reading, and observe the display update
automatically without a manual application restart. Settle the observation
window and criterion before execution. An application window that remains
open, or an unchanged displayed reading, cannot establish this outcome.

Available evidence: the illustrative requirement and plan texts above.
Performed software verification and result evaluation: NONE SUPPLIED.
Normal-operation pass: NONE SUPPLIED. Recovery check: NOT EXECUTED.
Historical result retained/reused: none is supplied in this example.
Supported conclusion: this plan's content omits the recovery condition.
Unsupported conclusion: whether the implemented viewer recovers or fails.

4. Closure and responsibility
Proposed requirement-owner action: settle and record the recovery
observation window and acceptance criterion through the governing process.
Proposed verification-owner action: update the actual plan/procedure
content to address interruption, restoration and new-reading updates;
retain the normal-operation check where it remains relevant.
Proposed trace-maintainer action: maintain the current artifact revisions
and applicable relationships so the revised content can be inspected.
Proposed later work: perform appropriate authorized verification, retain
its observations, evaluate them against the agreed criterion, and record
the evaluation for the designated reviewer.

Actual action owners and reviewer: UNASSIGNED.
Appointment path: the review lead brings this gap to the project manager
or delegated appointing role to name the requirement owner, verification
owner and reviewer, and identify who may decide reliance.
Actual appointment/request: NOT PERFORMED.
Clarification and plan/trace updates: PROPOSED, NOT PERFORMED.
Behavioral verification: NOT EXECUTED.

Closure criterion for the content gap: current verification content
addresses the added behavior and agreed criterion, with maintained links
and revisions. Behavioral support additionally needs appropriate performed
evidence and its evaluation. Authorized reliance needs its own disposition.

5. Recommendation and actual disposition
Evidence judgment: INSUFFICIENT for reliance on the recovery promise;
the documentary plan mismatch is identified within this illustration.
Recommendation: defer relying on this material as a demonstration of recovery;
assign clarification, content updates and later verification/evaluation.
Actual disposition: UNRECORDED. Actual deciding authority: UNKNOWN.
No release, delivery or tailoring decision is made by this record.
Limits: one documentary relationship, with assumed applicability; no
software execution, correction or successful recovery is demonstrated.
Reopen when the adopted basis, requirement, verification content, relevant
evidence or decision conditions change.

Why the proposed observation matters

A hypothetical viewer could update normally yet stop updating after reconnection. The proposed new-reading observation would distinguish that behavior from the recovery promise under the agreed criterion. This is reasoning about a possible implementation, not an executed counterexample or a prescribed reconnect mechanism.

Inspect the official plan-consistency requirement, SWE-071, then repeat this documentary comparison with your own revisions. The reproducible work here is reading the stated delta against the stated plan.

Follow the review in six steps

Download the spoken transcript.

Read the narration and on-screen details

1. Compare the change

On screen

  • One changed requirement
  • Old and new wording
  • Linked verification content
  • Worksheet includes decision and owner

Status: PROPOSED reader action; no real-project review is reported.

Narration

Start with one changed requirement and the decision that depends on it. Put the old and new wording side by side, identify the added condition and outcome, and open the linked verification content. The free worksheet keeps that comparison, its evidence limits and the next owner in one record.

2. Understand the recovery promise

On screen

  • Reading viewer teaching case
  • Connected updates retained
  • Automatic recovery added
  • No execution result supplied

Status: ILLUSTRATIVE teaching statements; software verification NOT EXECUTED.

Narration

In this illustrative case, a reading viewer updates its display while connected. The revised requirement adds automatic updates after the connection is interrupted and restored, without a manual application restart. These are chosen teaching statements. No application has been run, and no normal-operation or recovery result is available.

3. Read the linked plan

On screen

  • Plan keeps connection available
  • New reading is supplied in plan
  • No interruption or restoration
  • Recovery is absent from plan

Status: OBSERVED documentary mismatch within the illustration; software verification NOT EXECUTED.

Narration

The linked plan still keeps the connection available, supplies a new valid reading, and checks the display. It never interrupts or restores the connection. That is the documentary finding: the plan does not challenge the added condition. It tells us what is missing from planned verification, without showing whether the software recovers.

4. Locate the applicable obligation

On screen

  • Assumed adopted NPR 7150.2D
  • Assumed Class C mapping
  • SWE-071 invoked for exercise
  • Actual approval records absent

Status: ILLUSTRATIVE adopted-basis assumption; actual project approval UNRECORDED.

Narration

The exercise assumes adopted NPR 7150.2D and a Class C mapping invoking SWE-071, the plan-consistency provision. Real projects need their own applicability and authority records. The NPR mapping records the obligation; software traceability locates the related artifacts. Neither record supplies a performed result or a decision authorizing reliance.

5. Propose a discriminating observation

On screen

  • Interrupt and restore: proposed
  • New valid reading: proposed
  • Automatic-update observation: proposed
  • Observation window unresolved

Status: PROPOSED check; plan update NOT PERFORMED; verification NOT EXECUTED.

Narration

A proposed recovery check would interrupt the connection, restore it, supply a distinguishable new valid reading, and observe automatic updating without a manual application restart. An application window that remains open, or the previous reading, would not establish recovery. The requirement owner must resolve the observation window before execution. This check has not been executed.

6. Leave the decision with its authority

On screen

  • Recovery demonstration: defer reliance
  • Owner appointments: proposed
  • Verification: not executed
  • Actual disposition: unrecorded

Status: PROPOSED recommendation and appointments; actual disposition UNRECORDED.

Narration

Recommend deferring reliance on this material as a demonstration of recovery. Ask the project's appointing role to name owners for clarification, verification updates and review. Then obtain and evaluate appropriate authorized evidence. Here, those actions are proposed and actual disposition is unrecorded. The designated decision authority still needs to record the reliance disposition.

04 / Perform the comparison in order

How to review your own requirement change

  1. Select the claim and its decision. Identify the old and new requirement revisions. Write the changed trigger, outcome or constraint in ordinary language. State what someone wants to rely on now.
  2. Confirm the applicable basis. Locate adoption or incorporation, classification, the relevant RMM row and any authorized tailoring. Identify the decision authority. You can inspect a content gap while these records are missing, but retain the applicability question as unresolved.
  3. Open the linked content. Resolve the actual revision of each relevant plan, procedure or analysis. Read the steps, assertions or argument that supposedly address the change. Follow the relationship back to the requirement and explain any revision ambiguity. Inspect additional applicable relationships when the change affects them.
  4. Compare the criterion with available evidence. Identify the observation that would distinguish fulfillment from a plausible failure. Resolve ambiguous expectations with the responsible owner. Separate planned content from performed results and their evaluation; record absent material explicitly.
  5. Choose the smallest justified closure. If the content or evidence is inadequate, assign the missing clarification, update or verification. If existing evidence already addresses the change, record its relevant scope, revision fit and justified reuse rather than ordering a needless rerun. Preserve genuine older evidence with its original meaning.
  6. Record recommendation and disposition separately. State what the evidence supports and what remains open. Obtain the actual decision from the designated authority through the governing process. Retain its scope, conditions and reasons to revisit it.

The method combines maintained relationships with content inspection. NASA's SWE-052 handbook guidance, sections 3.3–3.5, supports identifiers, source references, ownership and change-impact review; the worksheet is one practical way to keep that work inspectable.

05 / Check the handoff

Before someone relies on the review

  • The adopted basis, relevant applicability and authority are identifiable or explicitly unresolved.
  • Old and new wording expose the changed condition and outcome.
  • The review cites actual relevant content and revisions, not only a link.
  • Planned criteria, performed evidence and evaluation remain distinguishable.
  • The conclusion fits the evidence's current scope and any justified reuse.
  • Open actions have owners or a concrete appointment path and closure criteria.
  • The actual disposition has a record, or remains UNRECORDED.

06 / Avoid false closure

Mistakes that leave the change unreviewed

Common record failures and the repair each needs.

Mistake / Why it misleads / Repair
Mistake Why it misleads Repair
Link to a moving document without identifying the reviewed revision A later reader cannot tell which content supported the judgment. Retain the relevant revision and location with the finding.
Rename the check or mark its link reviewed The record looks current while its actual steps still omit the new behavior. Update and review the verification content, then maintain the relationships.
Invent a convenient recovery deadline The check silently supplies a requirement decision nobody authorized. Have the responsible owner resolve the timing criterion before execution.
Use approval of a plan as proof of software behavior Permission or agreement to perform work becomes an imagined result. Keep plan approval, performed verification, evaluation and authorized reliance distinct.
Close the change ticket while follow-up work has no owner The missing evidence survives behind a completed administrative task. Retain an owned closure action and its evidence requirement in the governing workflow.

07 / Use Proof where the record already exists

An optional Proof view of recorded relationships

In an installed and configured Proof project with loaded requirements and recorded artifact links, this optional command displays those existing relations:

proof trace matrix --format csv

Run it from inside that project. Its rows identify loaded requirements; columns identify linked artifacts; cells display recorded relation types such as satisfies, verified_by, implemented_by and documented_by. For a record like the viewer example, such a view can help locate the requirement-to-plan link. The reviewer still opens the current plan and compares its content with the changed promise.

verified_by names a recorded relation. The display does not execute tests, assess recovery assertions, establish current target/result identity or evidence adequacy, calculate NASA compliance, approve tailoring or authorize acceptance. No command output is reported for this illustration. The worksheet remains usable on its own.

08 / Choose a maintainable workflow

Which record and method fit your decision?

Choose the smallest workflow that preserves the governing basis and lets another reviewer inspect the relevant content and evidence.

Workflow choices, with the work each leaves to the project.

Situation / Useful choice / What remains to establish
Situation Useful choice What remains to establish
One bounded change in an established review process A controlled document or issue using the worksheet. Chapter 6 permits suitable project formats addressing required content. Maintain revisions, evidence locations and the actual disposition. Chapter 6.
Several requirements share verification artifacts A maintained matrix or requirements tool with many-to-many relationships. Inspect the cases or analysis within each artifact; one document link may address only part of a requirement. SWE-052 guidance, sections 3.3–3.5.
The team already reviews work through repository issues and pull requests Keep the change comparison and its evidence references alongside that controlled workflow. NASA GCN provides a public project example of mappings to such records. GCN's Class D, non-safety-critical mapping is its own project assertion, not your applicability decision or an independent compliance endorsement. GCN matrix.
Requirements and artifact links are already loaded in Proof Use the optional trace-matrix display to locate recorded relationships. Judge current content, performed evidence and authority separately, as described above.

Use a content review for a documentary claim; select appropriate behavioral verification for an implemented-recovery claim. The method and any permitted evidence reuse must fit the governing requirements.

09 / Inspect the basis and repeat the comparison

Primary sources and documentary reproducibility

The official sources establish the provisions and their scope. The viewer's requirement wording, plan steps and revision labels are illustrative teaching material reproduced in the filled record. They are not NASA project records or an archived execution.

Primary references and the questions they answer.

Source / Use and limit
Source Use and limit
NODIS directive history and current NPR index Current issued edition and effective/expiration dates, checked 31 October 2026. Establish the project's adopted basis separately.
NPR Preface, P.2; Chapter 2, sections 2.1.7–2.2 Applicability, external incorporation, existing-project provisions, authority and tailoring. Read the qualifications with the requirement.
Chapter 3, sections 3.1, 3.5 and 3.12; Appendix D RMM maintenance, classification and class-specific traceability. Short class labels cannot assign a project classification.
Chapter 4, sections 4.1.5–4.1.6, 4.5 and 4.6.4 Change management, inconsistency closure, verification content, results evaluation and delivery provisions, each within applicability.
Appendix C, C.1–C.3 and relevant rows; Chapter 6, section 6.1 RMM meaning and recommended record content. This worksheet is not the full RMM or a mandated NASA format.
Version D SWE-052 handbook, history and sections 3.3–3.5 Current-versus-historical wording, maintained links, ownership and many-to-many relationships. Guidance does not turn a link into verified behavior.
NASA GCN project matrix An inspectable project mapping and workflow example. Its self-assessment remains scoped to that project.
OSMA handbook article, 18 May 2026 Official explanatory context. Its forward plan for E is not an issued replacement directive.

The original NPR PDF contains the complete directive. This guide relies on the relevant sections and selected mapping rows; it does not claim an exhaustive review of every obligation.

To reproduce the documentary finding, compare the filled record's old and new requirement texts, then inspect every listed step of VIEW-PLAN r1. Identify the absence of interruption/restoration and keep that conclusion separate from software behavior. There is no implementation, runtime prerequisite, test log or replay for this illustration. The proposed observation becomes execution evidence only after appropriate authorized work produces a retained, evaluated result.

10 / Apply the distinction elsewhere

Two more decisions this review can clarify

1. A changed document requirement may need a review

Illustrative, unperformed review. An operator-guide requirement now says the instructions must distinguish an unavailable reading from a valid zero reading. The linked review checks only that a troubleshooting section exists. A proposed content review should inspect whether the current instructions explain the distinction between those conditions.

That review can address the document requirement. It cannot establish that the application displays either condition correctly. Keep any application behavior claim with its own verification. The next action is to assign the document owner and reviewer, identify the revised text, and agree the content criterion.

2. A wording change may leave existing evidence useful

Illustrative reuse decision, no result supplied. A requirement replaces “data feed” with the already defined term “reading connection.” Suppose the owner confirms that the trigger, required outcome and scope are unchanged. The reviewer should inspect that equivalence and whether existing evidence still addresses the requirement.

If the actual current records support the same claim and the governing process permits reuse, record that support and its rationale. If the terminology change reveals a different interface or condition, follow that difference into verification. The decision depends on meaning and evidence fit, not merely a changed revision number.

11 / Resolve the remaining questions

NPR 7150.2D review questions, answered

Should I switch to E because a handbook article mentions it?

Use the issued directive record and your adopted project basis. At the 31 October 2026 check, NODIS lists D as current; OSMA's May article describes a forward plan for E. A planned revision does not establish a new binding edition. See the edition sources.

Can I identify this gap before software exists?

Yes. Comparing a changed requirement with planned verification can reveal that a condition is absent. Record a documentary finding and proposed work. A conclusion about implemented behavior awaits appropriate evidence.

Does the changed requirement always need a new test?

No. Existing verification may already address it, or an appropriate review or analysis may fit the claim. Inspect content and applicability first. A genuine new recovery condition still needs evidence that addresses that condition; another unrelated passing case cannot supply it.

Does “bidirectional” require two manually duplicated rows?

No. The relationship must be followable in both directions. The handbook describes maintained, sortable records and many-to-many relationships; it does not require duplicating each requirement in two manual rows. Use the guidance within your governing process.

Who can decide that an open item is acceptable for delivery?

The designated authority and governing delivery process determine that decision. Where SWE-194 applies, its wording includes requirements identified for delivery being met or dispositioned, approved changes implemented and designated defects resolved. The reviewer's recommendation is not that disposition. Section 4.6.4.